Texas Judges Back Enchanted Rock Bridge-to-Power Project, With a Catch

by Elisa Wood

Enchanted Rock Meta Bridge-to-Power
miss.cabul/Shutterstock.com
September 27, 2026
Share

Two administrative law judges last week recommended that Texas regulators approve a 366-MW bridge-to-power plant for Meta to be built by microgrid company Enchanted Rock.

The $499.8 million McCloud facility, an onsite power plant, would use 813 modular gas generators on 31 acres beside the data center that Meta-owned Wurldwide is developing. Local utility El Paso Electric would own the plant and contract with Enchanted Rock to install and operate it. 

For an initial bridge period of up to five years, the generators would operate as an island, electrically connected to the data center but not to El Paso Electric’s transmission system. The bridge ends when transmission improvements connect the data center and plant to the grid.

For more of our work, subscribe to our Substack or become a member

As a condition of approval, the judges said El Paso Electric must shield its other retail customers from the plant’s capital and operating costs for the life of the facility.

The judges questioned why El Paso Electric did not seek competing bids or evaluate other modular gas generators. The utility said Wurldwide preferred Enchanted Rock’s smaller units because they take up substantially less space than a traditional central plant.

The proposed decision now goes before the Texas Public Utility Commission. If the project is approved, the utility expects construction to finish in May 2027.

The project does not appear to be affected by Texas Gov. Abbott’s halt on new data center permit approvals in ERCOT because El Paso Electric is located outside of the grid operator’s territory. Abbott ordered the halt until the state completes an audit of how data centers are affecting resources and energy reliability within ERCOT.

As a next step, the Texas Public Utility Commission will consider the proposed decision. If the project wins approval, the utility expects the project to begin commercial operation in 2027.

The project is an example of how the microgrid play has changed with the rise of  large load data centers. While 10 megawatts was once considered large for a microgrid, they are now expanding in hundreds of megawatts. These larger projects often use the nomenclature “ onsite energy” rather than microgrid.

The Microgrid Dilemma: To Build Around the Grid or Wait for It?

Is it more economical for microgrids to build around the grid or wait for the grid to catch up? That’s one of the ideas I’ve been pondering since talking with Xendee’s Michael Stadler in this Energy Changemakers podcast conversation leading up to the June 8-10 University Week, a free virtual gathering focused on the latest […]

Elisa Wood
Xendee University Week

Inspiring Tales of Microgrid Innovation at the Top of the World

Rural regions of the world in Africa, Asia and Latin America should take note of Alaska’s microgrid success stories. 

Peter Asmus
Alaska's microgrid innovators

A Real Community Microgrid, At Last?

Pescadero, California, is planning a community microgrid that offers what few others do: resilience for pretty much the whole town.

Elisa Wood
Community microgrid in Pescadero
Let's Create a Decentralized Grid
Become an energy changemaker!
Click Here to Become a Member
Microgrids Now
Wood Energy Writers LLC
600 Twentyninth Place Ct #1055
Charlottesville, VA 22901
[email protected]
© Wood Energy Writers LLC. All rights reserved.
  • Terms of Service
  • Privacy Policy